World News
USA (197)
Bay Area
Bay Bridge (125)
Business (36)
Construction
2007 (3)
2006 (8)
2005 (7)
2004 (4)
2003 (3)
2002 (2)
Construction on Wikipedia
Construction on Web
Construction Books
Real Estate
|
|
|
| Sep.3 |
|
Bridge Is Back In Business The bridge reopen at 6 p.m., far ahead of the originally scheduled reopening of 5 a.m. Tuesday
| Crews spent the afternoon surveying the repair work
|
| | |
|
| Sep.2 |
|
Bridge Repairs Progressing Smoothly CalTrans reports it's possible the bridge may open before Tuesday morning. The last girder was removed by contractor C.C. Myers
|
| Aug.31 |
|
Bridge Closes; Caltrans Begins Work Caltrans began closing all onramps at 8 p.m. The crews have started the seismic retrofit operation that prompted the closure
| The bridge is closed through 5 a.m. Tuesday as crews replace a 350-foot section of the bridge just east of the Yerba Buena Island tunnel
|
| | |
|
|
| Dec.7 |
|
Final Skyway Segment Placed| After 3 years of preparation, the final concrete deck segment will be lifted into place. It was shipped from Stockton | |
|
| Oct.26 |
|
New Span Could Be Delayed Another Year Completion of the eastern span be delayed over a snag in moving an underwater power cable blocking construction
|
| |
Hwy 1. At Devil's Slide Reopens
|
| Jun.4 |
|
Complete Bridge Work Ahead of Schedule Overnight retrofit went so well that Caltrans will not need to close the lower deck again next weekend
|
| Apr.20 |
|
Contractor Named For Suspension Project American Bridge/Fluor Enterprises submitted a $1.43 billion bid, lower than the $1.68 billion submitted by the competitor
|
| Apr.18 |
|
$1.43 Billion Deal Should Complete Work The contract to build the final segment was awarded to a joint venture of American Bridge Co. and Fluor Enterprises
|
| Mar.22 |
|
Two Bids For Suspension Span $1.43 billion bid from American Bridge and Fluor. The other, $1.68 billion, from Kiewit, Koch, Skanska and Manson
|
| Jan.20 |
|
New Span Delayed Six Months State transportation officials seek more bids on the construction project to drive down ballooning costs
|
|
| Dec.8 |
|
Governor's Stall Cost State $81 Million A nearly yearlong delay in construction on the new eastern span cost taxpayers and toll-payers $81 million
|
| |
New Central Freeway Opens
|
| May.4 |
|
Feds: Bay Bridge Welds Not Faulty| Federal Highway Administration: Welds on the new eastern span are not faulty as had been alleged by ex-welders | |
|
| Apr.21 |
|
Sections Of Bay Bridge To Be Cut Out Inspectors hired by the feds will be cutting out some large sections to test the quality of its welding work
|
| Apr.15 |
|
No Faulty Welds Found In First Inspection Federal and state officials didn't find any problems in the first round of tests
|
| Apr.7 |
|
State: No Shoddy Work Claims on Bridge Dean Fryer of CalOSHA says inspectors are on site on a regular basis
|
| Apr.1 |
|
Bridge Costs Soar Stalled construction has not stopped the price tag for the project from jumping $300 million to $6.2 billion
|
|
| Dec.10 |
|
Simpler Plan Chosen for Span Schwarzenegger wants to scrap the expensive suspension design in favor of a cheaper skyway
|
| |
Tribe scales back plan to build casino
|
| Jul.31 |
|
Bridge Retrofit Costs Skyrocket The new eastern span is going to cost about 5 times as much as originally though
|
| May.27 |
|
Bridge bid comes in $1 billion over target| Only 1 contractor submitted a bid for the suspension portion of the new span, and job came in at $1.8 billion | |
|
|
| Oct.22 |
|
Bridge Work Won't Finish Until 2009 Steel companies accuse Caltrans of delaying the project The costs have tripled to an estimated $3 billion
|
| Aug.21 |
|
Bid for next phase far surpasses estimate The next construction phase of the bridge will cost $81 million more than the CalTran anticipated
|
| |
Bechtel wins giant Iraq contract
|
|
| Jan.29 |
|
Eastern span works begin Gov. Gray Davis kicked off the $2.6 billion dollar construction project
|
| Jan.23 |
|
$1.04 billion contract Caltrans awarded contract for construction of the eastern replacement span to Kiewit/FCI/Mason Joint Venture
Neighbor Real Estate:
Add a favorite (file a bookmark) to Bay Bridge, Construction Timeline
Please send feedback to: support@mapreport.com
Advertise on Bay Bridge, Construction Page
|